Fixing Broken Glass

Claim For Defects 

Navigating the process of claiming damages for defects under the Housing Development Act (HDA) requires clarity and strategic approach. Understanding your rights as a home buyer is crucial in ensuring developers uphold their responsibilities.

Defect Rectification: Home Buyer's Rights and Procedures

​

  • Statutory Sale and Purchase Agreement under the Housing Development (Control and Licensing) Act 1966:

    • Allows the home buyer to have defects rectified by the developer within the defect liability period.

    • the defect liability period ('DLP')is 24 months from the date of vacant possession.

​

  • Initial Procedure:

    • The home buyer serves a written notice to the developer.

    • The Developer must rectify defects within 30 days of receiving the notice.

​

  • If the Developer Fails to Act:

    • The home buyer issues a second written notice including a quotation from their own contractor.

    • The Developer is given an additional 30 days to rectify the defects.

    • If the developer still fails to act, the home buyer's contractor can proceed with the work.

    • The home buyer can claim the quotation sum from the developer.

​

  • The Law:

    • The home buyer retains the right to sue for defects under common law.

    • Reinforced by the Court of Appeal in Chrishanthini Angela Regina a/p Sebastiampillai v. View Esteem Sdn Bhd [2022] MLJU 2304:

      • the statutory Sale and purchase agreement does not bar purchasers from asserting common law rights to claim damages.

      • Provides a mechanism to ensure defects within 24 months after vacant possession are rectified, provided a 30-day notice is given.